Nansen Warming Hut Project Pictures

Phase 1 (Ground work, slab, parking) completed: 11/15/15.
Phase 2 (Raise frame, electric, enclose walls) completed 8/28/16.
Phase 3 (Insulate, Roofing, Solar Panels ) completed 10/30/16
Phase 4 (Heat, Windows & Doors) completed 1/19/17
Ongoing -Interior Gear racks, shelving, equipment storage and Historical Displays
(raising funds for this phase NOW)

January 21, 2017 – GRAND OPENING & Ribbon Cutting!